Skip to main content

November Wind Storm

Crews continue to work around the clock restoring power to our customers. We now have crews or servicemen assigned to all remaining outages in King County from the hurricane-force windstorm and are working toward restoring all remaining customers by or within a few hours of 6 p.m. tonight.

alert 

Safety first. Never touch or go within 35 feet of downed power lines because they might be energized. Call PSE at 1-888-225-5773 or 911 to report problems.

Report and track power outages online

Puget Sound Energy transmission line project

Electron Heights-Enumclaw transmission line and substation upgrades

2019 project updates

  • We are working on permitting, detailed design and easement acquisition for the 1.5 mile, 55 kV transmission line in Enumclaw
  • The route will travel along Garrett Street from Battersby Ave to Stevenson Ave..
  • We'll keep the community informed of our plans as they develop.
  • We completed Phase 1 in October 2009 and Phase 2 in July 2010.

Project overview

To increase reliability and meet growing customer demand for power, PSE is upgrading the existing 55 kilovolt (kV) substations and transmission lines between Electron Heights and Enumclaw to 115 kV.

These multi-year projects began in 2009 and include converting the voltage of over 20 miles of transmission line between the Electron Heights and Krain Corner substations; installing roughly 1.5 miles of new transmission line in Enumclaw; converting, upgrading or completely rebuilding five substations; and adding a fiber-optic line.

Current project in 2019

Build roughly 1.5 miles of 55 kV transmission line from a point outside the Enumclaw substation, along Garrett Street (following the existing distribution line) to a point on the existing 55 kV transmission line east of the Stevenson switching station. Take a closer look.

Additional projects in planning
  • Build a new Buckley substation off 112th St E and demolish our old Buckley substation.
  • Install a 115 kV capacitor bank within our Krain Corner substation on 268th Ave SE in Enumclaw.
  • Upgrade electrical equipment at our Enumclaw substation on Battersby Ave in Enumclaw.
  • Rebuild the Wilkeson substation from 55 kV to 115 kV and install a new 115 kV transformer and other related equipment. During construction, we will bring in a mobile substation unit to power the town reliably for nearby customers until the upgraded substation is complete.
  • Install a new fiber-optic line between the new Buckley substation and Krain Corner substation to improve communications amongst the new facilities.
  • Remove old 55 kV equipment from the Electron Heights switching station.
  • Convert the transmission system voltage from 55 kV to 115 kV.
Phase 2 (completed in 2010)
  • Electron Heights - Stevenson 115 kV transmission line rebuild: PSE rebuilt the final 12.2 miles of existing 55 kV transmission line to 115 kV transmission line standards from the Wilkeson substation to the Electron Heights switching station on Electron Rd in Orting.
Phase 1 (completed in 2009)
  • Electron Heights - Stevenson 115 kV transmission line rebuild: PSE rebuilt eight miles of existing 55 kV transmission line to 115 kV standards between our Stevenson switch on Stevenson Ave in Enumclaw and a location near the Wilkeson substation, located on Church St in Wilkeson.
  • The new transmission line will not be energized to 115 kV until the entire project is complete.

Contact us

We welcome your questions and comments! Please contact:
Peter McKenzie
Project Manager
1-888-404-8773
MajorProjects@pse.com

Learn more