Learn more about each step in the construction project process.

Electric and Gas
The first step towards getting natural gas and/or electric service to your construction project is to complete and submit the appropriate applications below.
Customer Journey diagram
Want to know what to expect during your project? Curious how long the typical project takes? Download our Customer Journey diagram.
Feasibility request
For a new or established business looking to expand or relocate with expected electric loads of 1MW or higher and/or gas load of 1900 SCFH or greater.
Public improvement
For projects that require coordination with multiple service providers in counties, cities and jurisdictions. (Municipalities Only)
Other inquiry
If you are interested in receiving assistance in determining your options for gas or electric service or have general questions you can contact us using out inquiry form.

Your PSE project manager will work with you to obtain the following items if they’re missing from your application:
- Official site address
- Accurate billing information
- Square footage
- Load information
- Panel amps
- Heating source
- A CAD drawing (or PDF) of your site plan

Your PSE project manager is reviewing your completed application and site plan. Your PSE project manager will:
- Create a timeline so you’ll know how long your project will take.
- Identify needed project dependencies such as permits and easements.
- Review everything which you once everything is ready to go.

Your PSE project manager will work with you in completing the following items:
- Cost estimate
- Proposed project agreement
- Easement documentation
- Request for City/County street use permits
- Submission of signed project agreements

After all the following project requirements have been completed PSE will coordinate to schedule your construction start date.
- Designs approved
- City/County street use permits approved
- Payment received (if applicable)
- City/County electrical inspection complete and posted
- Site Preparation Requirements have been met

PSE will coordinate the installation or modification of your gas or electric service.

Final steps to project completion:
- Customer obtains municipal inspection
- PSE coordinates meter installation following municipal inspection
- Provide your feedback by completing the PSE construction survey
- PSE CONNECTION COMPLETE!