2017 project updates

  • This project is currently in the design phase.
  • Permit applications are expected to be submitted in fall 2017.
  • Construction is expected to begin as early as spring 2018.
 

Project overview

 

To improve electric service reliability, PSE plans to rebuild the existing 1.5-mile transmission line between the Talbot Hill and PACCAR substations in Renton. We will replace aging equipment and increase the capacity of the local electric system, ensuring we can continue to serve customers reliably in the area well into the future.

We plan to rebuild the transmission line with higher-capacity wire and new poles that are similar to the existing poles. In some areas, the wood poles that support the existing transmission line also hold a distribution line; this configuration will remain after the project is complete.