East Enumclaw Substation
Upcoming planned power outages in the Greenwater and Crystal Mountain area
We're building a new substation in Enumclaw, near Commerce Street off Roosevelt Avenue. When it's up and running, Greenwater and Crystal Mountain will have more reliable power, and the area will be better able to handle growing demand.
To safely connect the new substation, we'll need to turn off power overnight for six nights in a row in the Greenwater and Crystal Mountain area.
Outage details:
- When: Nightly from 8 p.m. to 8 a.m., Dec. 1 through Dec. 6
- Where: Greenwater and Crystal Mountain
- How long: Up to 12 hours each night if backup power isn't available
- Questions? Contact Project Manager Jeff McMeekin at Major.Projects@PSE.com or call our Major Projects Hotline at 888.404.8773
How we're trying to keep the lights on. We know this is a busy time of year, and going without power for six nights is a real hardship. To help, we'll try to use the Crystal Mountain generator to provide backup power to parts of the community during the outages.
How many homes and businesses the generator can cover depends on how much power people use, so coverage may change from night to night. Customers in this area should plan to be without power for up to 12 hours each night.
Help power go farther. The less power everyone uses during outage hours, the more neighbors the generator can serve. Simple ways to save: lower your thermostat temperature, minimize appliance use and unplug unnecessary electronics during the outage window.
Thank you. We know these outages will be hard on residents and businesses. Completing this work now will allow the new substation to be connected to the grid sooner, providing increased electric reliability for the remainder of the winter storm season. By making these upgrades now, we can reduce the risk of unplanned outages during periods when reliable service is needed most. We'll keep the community updated as the work moves forward, and we appreciate our customers’ patience while we complete these improvements to make power more reliable for the Greenwater community.
Project overview
To increase reliability and meet growing customer demand for power, PSE is constructing a new substation in Enumclaw near Commerce Street, off Roosevelt Avenue. The substation will be used to transform power from 115 kV to 55/34.5 kV to improve service for the Greenwater and Crystal Mountain community. Additionally, this new substation is an important part of a larger electric reliability improvement effort which includes several electric upgrade projects between Electron and Enumclaw. We are converting the voltage of over 20 miles of transmission line between the Electron Heights and Krain Corner substations, and converting, upgrading or completely rebuilding five substations in the area. This project strengthens the electric system in the region by improving the reliability of our infrastructure and enabling us to better serve customers now and in the future.
Contact us
We welcome your questions and comments!
1-888-404-8773
Major.Projects@pse.com
Resources
Download additional project information.